ERRATUM regarding eligible costs – Applicant Guides for large and small projects, chapter 6.5.1 List of eligible expenditures

Date: 07 Feb. 2014

Due to a material error within the calls for large and small projects, in the Applicant Guides - Chapter 6.5.1 List of eligible expenditures, the following paragraph:

"The management and indirect costs shall not exceed 20% of the total eligible expenditures under the project."
is amended as follows:
"The management and indirect costs shall not exceed 20% of the total eligible direct expenditures under the project.”

In this respect, in Annex 2 - Project Budget to the Applicant Guides for large and small projects, the following budget line:
"5. * Indirect costs (up to 20% of the total direct eligible costs) "
is amended as follows:
"5. Indirect costs *"